Target Class Page of the Reclass Wizard
Use this page to select the class that Cobra will modify through the Reclass process.
This page only displays classes for which you have view and update access.
Contents
Field | Description |
---|---|
Class | Click
to display the Class Lookup dialog box, where you can select a target class based on the following rules:
If you select progress as a target class, Cobra will not copy any data to future periods. This means:
You can reclass a budget class that uses calendar set 00 to a forecast class that uses a different calendar set even if the budget is at the work package level and the forecast is at the control account level. You cannot reclass a class that uses a calendar set other than 00 into a class that uses calendar set 00. |
Class Type | This field displays the type of the selected target class. |
Class Description | This field provides a brief description of the selected target class. |
Add to existing | This option adds the value in the source class to the value in the target class. This option is helpful when reclassing an approved scope change into the budget class.
If you select this option and there are spread curves assigned to the resource assignments, Cobra changes the curves to Manual. |
Replace existing | This option replaces the value in the target class with the value in the source class for all selected costs. This option is useful when replacing the customer's forecast with a CAM's forecast. The final result does not double the original value. It replaces any class in that work package or control account with the new class.
If you select this option and there are spread curves assigned to the resource assignments, Cobra uses the existing spread curve assigned to the source class. If you delete a spread curve, and then run reclass, Cobra retains that spread curve assigned the source class and changes it to Manual for the target class regardless of the option you select on this page. |